Best GPU Neoclouds 2026: CoreWeave, Nebius, Lambda, Crusoe, and Groq Ranked by Published Pricing and Contracted Power
The ‘neocloud’ label now covers 5 corporations with very completely different enterprise fashions. CoreWeave and Nebius are public corporations that publish quarterly outcomes and file reviews with the SEC (CoreWeave on Form 10-Q, Nebius as a international non-public issuer on Form 6-Ok). Lambda and Crusoe are non-public and heading towards IPOs. Groq has run GroqCloud on its LPU structure since 2024; after licensing that expertise to NVIDIA in December 2025, the impartial Groq refocused fully on inference-cloud infrastructure. This article compares them on what really issues to a purchaser: printed pricing, deployed and contracted energy, {hardware} roadmap, contract construction, and impartial high quality rankings.
TL;DR
- CoreWeave is the one Platinum-rated GPU cloud in SemiAnalysis ClusterMAX 2.0 and instructions premium listing pricing on H100, H200, and B200.
- Nebius is the one supplier right here publishing B300 on-demand pricing; Lambda publishes the bottom B200 on-demand fee.
- Lambda nonetheless publishes the most cost effective on-demand B200 ($6.69/GPU-hr) however has no spot tier.
- Crusoe is the one supplier right here with AMD MI300X/MI355X on its fee card.
- Groq is now an NVIDIA Cloud Partner and plans so as to add NVIDIA GPU capability alongside its LPU inference cloud.
CoreWeave / Nebius / Lambda / Crusoe / Groq
| Metric | CoreWeaveNASDAQ: CRWV | NebiusNASDAQ: NBIS | LambdaPrivate · IPO H2’26 (rep.) | CrusoePrivate · ~$10B+ | GroqPrivate · $3.5B |
|---|---|---|---|---|---|
| Published valueNVIDIA HGX H100 · $/GPU-hr |
$6.16
node value ÷ GPUs |
$3.85
HGX, on-demand |
$3.99
SXM, 8x occasion |
$3.90
HGX, on-demand |
—
per-token solely |
| Q2 2026 incomenewest reported |
$2.58B
+112% YoY · internet loss $626M |
$582M
+454% YoY · ARR $3.0B |
n/d
>$520M FY Sep-25 (The Information) |
n/d
non-public; ~$3B elevate at ~$30B reported (Jul) |
n/d
$1B raised in 2026 (Jun + Aug) |
| Powerlively / contracted |
1.5 GW
4.2 GW+ contracted · 51 DCs |
~1 GW
linked goal YE26 · 5 GW contracted goal |
n/d
15 US DCs · KC web site 24→100+ MW |
~0.2 GW
Abilene energized · 4.9 GW contracted (Jun) |
54 MW
→ 200+ MW in 2027 · 13 DCs |
| ClusterMAX 2.0SemiAnalysis tier |
Platinum
Only Platinum supplier, 2 rankings operating |
Gold
Top of Gold tier |
Silver
No spot tier; on-demand self-serve |
Gold
Only AMD on the speed card |
Not rated
Inference API at time of score |
| Anchor offersdisclosed |
Meta, Anthropic, OpenAI
~$104B backlog (+>$25B early Q3) |
Microsoft $17.4B (to $19.4B)
Meta $3B + as much as ~$27B |
Microsoft multibillion, GB300 NVL72
NVIDIA ~$1.5B lease-back (rep.) |
Oracle/OpenAI Abilene 1.2 GW
Microsoft 900 MW campus |
NVIDIA licensed LPU tech (~$20B rep.)
6M+ builders on GroqCloud |
| Next-gen siliconstanding Aug 2026 |
Vera Rubin NVL72: first bring-up + validation (Q2)
|
Vera Rubin NVL72 models obtained; validating
|
Vera CPU + Quantum-X800 CPO launch accomplice
|
Vera CPU launch assist; MI355X through gross sales
|
NVIDIA LPX (Groq tech); NCP licensed Aug 12; GPU capability deliberate
|
| Discounts & egressprinted |
Reserved as much as 60% off · egress free
|
Commit as much as 35% off · community egress free (Std object egress $0.015/GiB)
|
Sales-quoted · egress free · no spot
|
Sales-quoted · egress free
|
Per-token pricing · clusters sales-led
|
| Funding posture2026 |
$35–39B capex information · $31B recourse debt · $3.1B time period mortgage · $1B Jane Street
|
$4.3B converts (H1) · $5.0B converts priced Aug 19 · $775M secured · >$9B prepayments anticipated
|
$1.5B+ Series E (Nov) · $1B credit score facility (May) · $350M pre-IPO (rep.)
|
$1.375B Series E at >$10B · $7.1B JV development mortgage (Abilene ph.2)
|
$650M (Jun) + $350M Series A at $3.5B (Aug), NVIDIA collaborating
|
Cheapest printed
H100 on-demand at Nebius. Lambda has the bottom B200 at $6.69; Crusoe the bottom H200 at $4.29. Nebius is the one one itemizing B300 on-demand.
Premium, and why
SemiAnalysis says CoreWeave instructions that per GPU-hour over Nebius, Crusoe and Lambda on managed clusters. It is the one Platinum ClusterMAX supplier, twice.
What capability actually clears at
per MW on Q3 short-term offers at Nebius, versus ~$12M on its 2026 base. Four Q2 offers averaged >$1B every; 70% had been pay as you go.
1. Who these corporations are in 2026
CoreWeave (Nasdaq: CRWV) reported Q2 2026 income of $2.575 billion, up 112% yr over yr, with a income backlog of roughly $104 billion. That backlog excludes greater than $25 billion of recent commitments added in early Q3. Active energy reached 1.5 GW and contracted energy reached about 3.7 GW as of June 30; CoreWeave’s information middle web page now states 4.2 GW+ contracted throughout 51 information facilities. The firm accomplished the {industry}’s first bring-up and validation of NVIDIA Vera Rubin NVL72 in the course of the quarter. Net loss was $626 million, pushed by $640 million in internet curiosity expense. (CoreWeave Q2 2026 release, CoreWeave AI data centers page)
Full-year 2026 steering is $12.4–13.2 billion in income and $35–39 billion in capex. Management expects greater than 1.85 GW of lively energy by yr finish. (CNBC)
Nebius Group (Nasdaq: NBIS) reported Q2 2026 group income of $582.3 million, up 454% yr over yr. AI cloud income was $574.9 million, up 514%, with annualized run-rate income of $3.0 billion. The AI cloud phase posted a 49.7% adjusted EBITDA margin. Q2 capex was about $5.7 billion, and the corporate ended the quarter with $8.0 billion in money. Nebius raised its year-end 2026 contracted energy goal to five GW and plans to deploy greater than 1 GW per yr beginning in 2027.
Lambda is non-public. It closed a Series E of greater than $1.5 billion led by TWG Global in November 2025 and a $1 billion senior secured credit score facility (J.P. Morgan lead arranger) in May 2026. Michel Combes, former CEO of SoftBank International and Sprint, grew to become CEO in May 2026; co-founder Stephen Balaban moved to CTO. Lambda has a multibillion-dollar, multi-year settlement with Microsoft protecting tens of 1000’s of NVIDIA GPUs, together with GB300 NVL72 programs. The Information has reported an IPO goal of H2 2026, however no public S-1 exists as of this writing.
Crusoe is non-public. It raised a $1.375 billion Series E at a valuation above $10 billion in October 2025, led by Valor Equity Partners and Mubadala Capital. In July 2026, Bloomberg reported Crusoe was in talks to boost roughly $3 billion at a valuation close to $30 billion. Crusoe builds the 1.2 GW Abilene, Texas campus for Oracle and OpenAI (the primary Stargate web site). In March 2026 it introduced a separate 900 MW Abilene campus for Microsoft, bringing the total web site to about 2.1 GW. On June 9, 2026, Crusoe mentioned its contracted AI infrastructure reached 4.9 GW throughout 5 US campuses and Crusoe Cloud, with a growth pipeline above 40 GW.
Groq launched GroqCloud in March 2024 round its LPU inference chip. It modified form in December 2025, when NVIDIA signed a non-exclusive license for Groq’s inference expertise in a transaction reported by CNBC at about $20 billion. Founder Jonathan Ross, president Sunny Madra, and different employees joined NVIDIA. Groq stayed impartial, and GroqCloud stored operating. Since then, Groq raised $650 million in June 2026 and a $350 million Series A in August 2026 at a $3.5 billion valuation, with deliberate NVIDIA participation. Groq now operates 13 information facilities and expects to scale from 54 MW to 200+ MW in 2027. On August 12, 2026 it joined the NVIDIA Cloud Partner program and mentioned it plans to deliver NVIDIA accelerated computing on-line “sooner or later”; that GPU capability is just not but a broadcast service. Adam Winter is CEO; Alex Davis of Disruptive is Executive Chairman.
2. Published on-demand pricing (per GPU-hour, USD)
Prices under had been learn instantly from every supplier’s pricing web page on August 21, 2026. CoreWeave lists per-node costs; per-GPU values are the node value divided by GPU depend. CoreWeave’s web page additionally reveals the similar per-GPU determine as its “inference single GPU” value. Groq doesn’t publish GPU-hour pricing; GroqCloud is priced per token, and NVIDIA GPU cluster entry is a deliberate providing dealt with by gross sales. CoreWeave spot costs fluctuate by area; the figures under are the North America charges.
| GPU | CoreWeave | Nebius | Lambda | Crusoe |
|---|---|---|---|---|
| NVIDIA GB300 NVL72 | Contact gross sales | Contact gross sales | — | — |
| NVIDIA HGX B300 | Contact gross sales (spot $4.48) | $7.85 (preemptible $4.30) | — | — |
| NVIDIA GB200 NVL72 | $10.50 (4-GPU occasion $42.00) | Contact gross sales | — | Contact gross sales |
| NVIDIA HGX B200 | $8.60 (8-GPU node $68.80; spot $4.26) | $7.15 (preemptible $3.95) | $6.69 | Contact gross sales |
| NVIDIA HGX H200 | $6.31 (spot $2.62) | $4.50 (preemptible $2.45) | — | $4.29 |
| NVIDIA HGX H100 | $6.16 (spot $2.46) | $3.85 (preemptible $2.15) | $3.99 | $3.90 |
| NVIDIA A100 80GB SXM | $2.70 | — | $2.79 | $2.30 |
| AMD MI355X | — | — | — | Contact gross sales |
| AMD MI300X | — | — | — | $3.45 |
| Network egress | Free | Free (Standard object storage egress $0.015/GiB) | Free | Free |
| Committed-use low cost | Up to 60% | Up to 35% | Sales-quoted | Sales-quoted |
What the desk reveals
CoreWeave expenses a premium and publishes probably the most full card. Its H100 fee of $6.16/GPU-hr is about 60% above Nebius and Lambda. SemiAnalysis reviews CoreWeave instructions roughly 10–15% extra per GPU-hour than Nebius, Crusoe, Lambda, and Fluidstack on managed Slurm or Kubernetes clusters, and that its pricing sits nearer to the large hyperscalers. CoreWeave can also be the one one of many 4 publishing a GB200 NVL72 on-demand value.
Nebius undercuts CoreWeave on Blackwell and is the one one with B300 on-demand. Its B200 fee of $7.15 is under CoreWeave’s $8.60, and its $7.85 B300 fee has no printed competitor on this group. Preemptible charges run roughly 45% under on-demand.
Lambda holds the most cost effective printed B200 occasion at $6.69. Its 1-Click Clusters (16 to 2,000+ GPUs, 2-week to 1-year phrases) are priced greater: $9.86, $9.36, and $8.87 per B200-hour at 16, 64, and 256+ GPUs respectively. Lambda has no spot tier. Third-party trackers notice Lambda raised its H100 SXM fee from $2.99 to $3.99 over 2025–2026 as demand outran provide.
Crusoe is the one AMD possibility and the most cost effective H200 at $4.29. Its H100 fee of $3.90 is near Nebius and Lambda. B200, GB200, and MI355X require a gross sales dialog.
List costs understate the market. Nebius disclosed that its Q2 2026 offers averaged greater than $20 million in annual contract worth per MW, that the 2026 base is priced close to $12 million per MW, and that Q3 short-term capability offers are clearing above $40 million per MW. The firm additionally ran its first capability public sale.
3. Deployed and contracted energy
| Provider | Active / linked energy | Contracted or deliberate | Notable websites |
|---|---|---|---|
| CoreWeave | 1.5 GW lively (Q2 2026); >1.85 GW anticipated by YE 2026 | ~3.7 GW contracted at June 30; 4.2 GW+ per present firm web page | 51 information facilities, North America and Europe |
| Nebius | Up to ~1 GW linked focused by YE 2026 | 5 GW contracted by YE 2026; >1 GW/yr from 2027 | New Jersey, Missouri, Oklahoma, Alabama, Kansas City, UK, Finland, France, Israel, Estonia, Iceland |
| Lambda | Not disclosed; 15 US information facilities per firm | Microsoft deal (tens of 1000’s of GPUs); Kansas City web site 24 MW → 100+ MW | Liquid-cooled US websites; 10,000+ Blackwell Ultra manufacturing unit with Quantum-X800 CPO |
| Crusoe | Abilene section 1: two ~100 MW buildings energized | 4.9 GW contracted throughout information facilities and cloud (June 2026); Abilene 1.2 GW (section 2 by YE 2026) + 900 MW Microsoft campus (first constructing mid-2027); 1.8 GW Wyoming campus | Five US campuses incl. Abilene TX, two extra in Texas, Missouri; Wyoming; Iceland, Norway |
| Groq | 54 MW | 200+ MW in 2027 | 13 information facilities throughout North America, Europe, Middle East, APAC |
4. Hardware roadmap and entry to next-gen silicon
Vera Rubin: CoreWeave says it accomplished the {industry}’s first bring-up and system-level validation of Vera Rubin NVL72 in Q2 2026. Nebius says it has obtained its first Vera Rubin NVL72 programs and is validating compute, networking, and orchestration forward of manufacturing availability. Lambda was a GTC 2026 launch accomplice for NVIDIA’s Vera CPU and Quantum-X800 InfiniBand co-packaged optics. Crusoe introduced launch assist for the Vera CPU and NVIDIA Nemotron 3 fashions. None of the 4 publishes Rubin pricing but.
Blackwell Ultra (B300 / GB300): Nebius is the one supplier with a public B300 on-demand value. CoreWeave lists GB300 NVL72 and HGX B300 as contact-sales, with a B300 spot fee of $35.84 per 8-GPU node. Lambda’s Microsoft contract consists of GB300 NVL72 programs. Nebius’s Microsoft contract was reported to cowl greater than 100,000 GB300 chips.
AMD: Crusoe is the one one of many 5 with AMD Instinct MI300X on its on-demand card and MI355X accessible through gross sales. CoreWeave, Nebius, and Lambda stay NVIDIA-only on their public pages. Groq’s LPU is the opposite non-NVIDIA accelerator on this group, however it’s offered per token, not per GPU-hour.
Groq LPU and NVIDIA LPX: NVIDIA introduced its LPX platform, incorporating licensed Groq inference expertise, at GTC 2026. Groq says its capital will fund fit-out of current information facilities with LPX programs and NVIDIA GPU clusters. Groq’s personal LPU stays the engine behind GroqCloud’s token API.
5. Contract construction and who the anchor clients are
| Provider | Anchor clients (disclosed) | Contract mannequin |
|---|---|---|
| CoreWeave | Meta, Anthropic, OpenAI, Microsoft (traditionally), plus Cognition, Databricks, Hudson River Trading, Runway, Jane Street | Multi-year take-or-pay; ~$104B backlog; reserved as much as 60% off; on-demand and spot printed |
| Nebius | Microsoft ($17.4B base, as much as $19.4B); Meta ($3B Nov 2025; second settlement as much as ~$27B, Mar 2026); Reflection, Cohere, a US quant agency | 3 tiers: short-term 3–6 month premium offers, 1–3 yr core contracts, long-term investment-grade contracts; ~70% of Q2 offers pay as you go |
| Lambda | Microsoft (multibillion), NVIDIA (reported ~$1.5B lease-back of ~18,000 GPUs) | On-demand self-serve; 1-Click Clusters 2 weeks–1 yr; reserved through gross sales |
| Crusoe | Oracle/OpenAI (Abilene lease), Microsoft (900 MW campus) | On-demand, spot, reserved; plus long-term information middle leases as a developer |
| Groq | 6M+ builders, Fortune 500 enterprises | Per-token serverless inference; NVIDIA GPU clusters deliberate, sales-led |
Sources: Nebius 6-K on Meta agreement, Nebius 6-K on secured financing, DCD on Nebius–Meta, DCD on Lambda–NVIDIA
The Nebius–Meta construction is value studying intently. The March 2026 settlement consists of $12 billion of devoted 5-year cluster orders beginning early 2027. An additional order provides Meta entry to unsold capability on specified clusters, and obliges Meta to purchase that capability if Nebius can not promote it to others. That is successfully a ground on utilization for the lined clusters. (SEC 6-K)
6. Which supplier matches which workload
Frontier-scale coaching (10,000+ GPUs, multi-year): CoreWeave and Nebius are the 2 public suppliers right here with SEC-reported monetary scale and demonstrated NVL72 rack-scale working expertise. CoreWeave has the reliability monitor document and Platinum score. Nebius has higher dedicated pricing and is promoting 2027 capability now. Both have Vera Rubin models in hand.
Mid-size coaching and fine-tuning (16–512 GPUs, weeks to months): Lambda’s 1-Click Clusters and Nebius’s on-demand B200/B300 are probably the most accessible. Crusoe’s H200 at $4.29 is the most cost effective Hopper-class possibility for memory-heavy jobs.
Budget-sensitive experiments: Nebius preemptible H100 at $2.15 and CoreWeave spot H100 at $2.46 per GPU are the bottom printed charges right here. Lambda has no spot tier.
AMD GPU analysis: Crusoe is the one selection on this group.
Low-latency inference at excessive token quantity: GroqCloud’s per-token LPU endpoints stay the distinctive providing. Nebius Token Factory and Crusoe Managed Inference are the GPU-based options with printed per-token charges.
Buyers needing a public steadiness sheet: Only CoreWeave and Nebius publish quarterly outcomes and file with the SEC. Both corporations’ annual statements are audited; the Q2 figures used listed here are unaudited quarterly outcomes.
Sources
- CoreWeave, “CoreWeave Reports Strong Second Quarter 2026 Results,” Aug 11, 2026 — https://buyers.coreweave.com/information/news-details/2026/CoreWeave-Reports-Strong-Second-Quarter-2026-Results/default.aspx
- CNBC, “CoreWeave (CRWV) Q2 earnings report 2026,” Aug 11, 2026 — https://www.cnbc.com/2026/08/11/coreweave-crwv-q2-earnings-report-2026.html
- CoreWeave pricing web page — https://www.coreweave.com/pricing
- Nebius, “Nebius reviews second quarter 2026 monetary outcomes” (PDF), Aug 12, 2026 — https://belongings.nebius.com/belongings/72a8c258-bbb7-4df7-ab9d-8698f6cb88fc/PR.pdf
- Nebius, “Letter to shareholders Q2 2026” (PDF), Aug 12, 2026 — https://belongings.nebius.com/belongings/a6ecfd85-a6cb-4967-8ef7-9a25bd261f9c/SHLQ226.pdf
- Nebius pricing web page — https://nebius.com/costs
- Nebius Group Form 6-Ok (Meta settlement), Mar 2026 — https://www.sec.gov/Archives/edgar/information/1513845/000110465926027886/tm268879d1_6k.htm
- Nebius Group Form 6-Ok (secured financing), Jul 2026 — https://www.sec.gov/Archives/edgar/information/0001513845/000110465926084452/tm2620683d1_ex99-1.htm
- Lambda pricing web page — https://lambda.ai/pricing
- Lambda, “$1 Billion Senior Secured Credit Facility,” May 7, 2026 — https://lambda.ai/weblog/lambda-closes-1-billion-senior-secured-credit-facility
- Lambda, “Leadership Team” announcement, May 2026 — https://lambda.ai/weblog/lambda-assembles-leadership-team-to-power-gigawatt-scale-ai-infrastructure
- Lambda, Microsoft settlement, Nov 3, 2025 — https://lambda.ai/weblog/lambda-announces-multibillion-dollar-agreement-with-microsoft-to-deploy-ai-infrastructure-powered-by-tens-of-thousands-of-nvidia-gpus
- Crusoe pricing web page — https://www.crusoe.ai/cloud/pricing
- Crusoe, Series E announcement — https://www.crusoe.ai/sources/newsroom/crusoe-announces-series-e-funding
- Crusoe, 900 MW Microsoft campus, Mar 27, 2026 — https://www.crusoe.ai/sources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure
- Groq, NVIDIA licensing settlement, Dec 2025 — https://groq.com/newsroom/groq-and-nvidia-enter-non-exclusive-inference-technology-licensing-agreement-to-accelerate-ai-inference-at-global-scale
- Groq, $650M elevate, Jun 22, 2026 — https://groq.com/newsroom/groq-raises-usd650m-to-scale-its-ai-inference-cloud-business
- Groq, $350M Series A, Aug 17, 2026 — https://groq.com/newsroom/groq-closes-usd350-million-series-a-building-the-world-s-leading-ai-inference-cloud
- CNBC, NVIDIA–Groq deal, Dec 24, 2025 — https://www.cnbc.com/2025/12/24/nvidia-buying-ai-chip-startup-groq-for-about-20-billion-biggest-deal.html
- SemiAnalysis, “ClusterMAX 2.0,” Nov 2025 — https://e-newsletter.semianalysis.com/p/clustermax-20-the-industry-standard
- SemiAnalysis ClusterMAX CoreWeave assessment — https://www.clustermax.ai/cloudreview/coreweave
- DCD, Nebius–Meta and capability targets — https://www.datacenterdynamics.com/en/information/nebius-signs-3bn-deal-with-meta-says-current-available-capacity-is-sold-out-as-it-targets-25gw-by-end-of-2026/
- DCD, Lambda pre-IPO funding report — https://www.datacenterdynamics.com/en/information/lambda-in-talks-to-raise-350m-in-pre-ipo-funding-report/
- TechCrunch, Groq $350M pivot — https://techcrunch.com/2026/08/17/groq-raises-350m-to-fuel-its-pivot-from-ai-chips-to-neocloud/
- SiliconANGLE, Crusoe $3B talks — https://siliconangle.com/2026/07/03/ai-data-center-builder-crusoe-reportedly-raising-3b-30b-valuation/
- CoreWeave, AI information facilities web page (51 DCs, 4.2 GW+ contracted) — https://coreweave.com/ai-data-centers
- Crusoe, “Contracted AI Infrastructure Capacity Approaches 5 Gigawatts,” Jun 9, 2026 — https://www.crusoe.ai/sources/newsroom/crusoes-contracted-ai-infrastructure-capacity-approaches-5-gigawatts-across-data-centers-and-cloud
- Groq, “Groq Becomes an NVIDIA Cloud Partner,” Aug 12, 2026 — https://groq.com/newsroom/groq-becomes-an-nvidia-cloud-partner
- Nebius Group Form 6-Ok, pricing of $5.0B convertible notes, Aug 20, 2026 — https://www.sec.gov/Archives/edgar/information/0001513845/000110465926098924/tm2623617d1_6k.htm
- Newmark, $7.1B development mortgage for Abilene JV — https://www.nmrk.com/insights/press-releases/newmark-facilitates-7-1-billion-construction-loan-to-develop-ai-data-center